In brief
A site on this type of flexible grid connection relies on instructions from the local electricity network operator. If those instructions stop reaching it, the site may have to reduce or stop the flow of power as a precaution. This automatic response is called a fail-safe.
The connection terms set out what the site must do if it loses contact, including any restrictions on importing or exporting power. These requirements can affect the site’s operation and commercial performance, making it important to plan and test the communications link before the site goes live.
How flexible connections let sites connect sooner
A project can be ready to connect before the local electricity network has enough capacity to accommodate it. The distribution network operator (DNO), which owns and runs the local network, may need to install a larger transformer or lay a new cable. A flexible connection can let the project go ahead before those upgrades are complete. In return, the site agrees to reduce how much electricity it imports or exports when the network is constrained. This reduction is known as curtailment.
UK Power Networks, for example, explains that generator owners can avoid the upfront cost and delay of network upgrades by agreeing to reduce their exports at certain times (UK Power Networks, 2026). Scottish and Southern Electricity Networks (SSEN) Distribution provides a curtailment report as part of its Technical Limits offers. It also tells customers to plan for reliable communications and to allow for additional equipment and communications costs at the connection point (SSEN Distribution, 2026b).
How grid instructions reach the site
The electricity network operator sends the site a limit on how much power it can draw from or send to the grid. That limit is called a set point. Equipment at the substation receives the instruction and passes it to the site’s controller, which keeps the site within the limit.
The instructions can pass through equipment and links that different parties are responsible for. For example, National Grid Electricity Distribution (NGED) sends instructions over its own network to equipment at the substation. A control panel then passes the limit to the site’s controller (NGED, 2025). In SSEN Distribution’s guidance, the site owner installs the link between its controller and the network operator’s equipment (SSEN Distribution, 2026c). The important question for the project team is where the network operator’s responsibility ends and the site owner’s begins.
Figure 1 · Communications path
Who is responsible for the links that carry instructions to the site?
|
The DNO’s part
|
Network control system (ANM)
The DNO’s control system, which sends each site its limits as set points
Communications link used by the electricity network operator
|
|||
|
Varies by scheme
|
Substation equipment (RTU or ANM outstation)
At the site’s substation
Connection control panel
Used in some schemes to present the limit to the site’s controller
Link to the site’s controller
|
|||
|
The site owner’s part
|
Site controller
Controls the site’s import or export within the limit
|
|||
|
A failure on any link in this path can trigger the site’s fail-safe, whichever party is responsible for the link.
|
||||
What happens when the site loses contact?
Imagine a battery storage site that’s due to send power to the grid during the evening peak. The battery is charged and the grid has room for the power, but the site loses the link that carries instructions from the electricity network operator. If the site’s fail-safe limit is zero, it has to stop exporting once the fail-safe takes effect. It may not be able to export again until the link is restored and, where required, the equipment is reset.
That’s a different cause of curtailment from a shortage of grid capacity. UK Power Networks’ dashboard, for example, records customer communications failures separately from curtailment caused by network constraints (UK Power Networks, 2025).
How quickly the fail-safe takes effect and what’s needed to resume operation depend on the scheme. For your own project, check the connection agreement and consider how interruptions caused by communications failures could affect the site’s operation and commercial performance. Understanding these requirements early helps the project team determine where communications resilience is needed and how quickly connectivity must be restored.
Will a backup link help?
A backup only helps if it still works when the main link fails. Two mobile connections can look separate but still rely on the same mobile core, the part of the network that connects devices and routes their data. If that core fails, both connections can lose data service even when there’s still a mobile signal. The same principle applies on site: two links that share a router or power supply can both go down if that equipment fails.
The next question is how quickly the backup can take over. The equipment has to notice the fault, switch connections and get data flowing again. Test how long that takes with the equipment and settings the site will actually use, then compare it with the time allowed under the connection scheme. Even if the backup isn’t fast enough to prevent the fail-safe from taking effect, it may still shorten the interruption.
What to check before the site goes live
For each link between the network operator and the site’s controller, ask:
- Which rules apply? Record the connection agreement and the version of any guidance it refers to.
- Who is responsible? Confirm who owns each link and who restores it if it fails.
- What happens if contact is lost? Check when the fail-safe takes effect, what limit applies and whether normal operation resumes automatically or needs a reset.
- Could one fault take out both links? Check whether the main and backup connections share a mobile core, equipment or power supply.
- How long does it take to get data flowing again? Agree how the project team will test the loss of each link and its power supply before the site goes live. Compare the measured recovery time with the time the connection scheme allows.
How CSL can help with site communications
CSL already supports connectivity at renewable-energy sites and across critical utilities. Whether you’re developing a new connection, managing an existing site or supporting network operations, CSL can help identify communications requirements, assess potential points of failure and select connectivity solutions suited to the application. The site’s communications design needs to meet the requirements set by the local electricity network operator in the grid connection agreement.
Where mobile connectivity is suitable, CSL DualCore® gives the site two mobile connections that don’t rely on the same core network. This can be delivered through rSIM® technology in the site’s equipment or through a CSL DualSIM® Router configured for core independence. rSIM is configured to check whether data is getting through and can switch automatically to a backup mobile network when it detects a failure.
Where a site needs more capacity or a mix of connection types, CSL Outpost can combine mobile, satellite and fixed-line connections into one managed service. If one communications link drops, the others can keep carrying data.
CSL can also manage private routing and encrypted connections where the site needs them.
Planning a new grid connection or reviewing communications at an existing site? Talk to CSL’s team about which links need a backup and how to test that it works.
Sources
- NGED (2025). Active Network Management Guidance, National Grid Electricity Distribution, 25 February 2025.
- SP Energy Networks (2024). Accelerating Distribution Connections, 15 May 2024.
- SSEN Distribution (2026b). Technical Limits at our Grid Supply Points, accessed 23 November 2026.
- SSEN Distribution (2026c). REF-NET-COM-027 Flexible & Curtailable Connections: Offer Guidance, Revision 1.00, July 2026.
- UK Power Networks (2025). DERMS Access Products and their Operational Implementation, Version 1.0, May 2025.
- UK Power Networks (2026). Flexible connections, accessed 23 November 2026.